Author: admin

  • Project Update4

    DECEMBER 2023 Slab Edge Ongoing  (New slab edge 3) (New slab edge 4) (New curb 1) (New curb 2) Framing, Insulation, DensGlass and Waterproofing  Framing 2 (DensGlass install 1) (DensGlass-waterproofing caulk) (Waterproofing 1) Waterproofing 2 Traffic Coating Preparation  Walkway Slab Prep 2

  • Project Update3

    NOVEMBER 2023 Slab Edge Demolition  Slab Edge Demo 2 Steel Rust Inhibitor Application and Framing  Electric Rough-in  Insulation and Framing Start

  • Project Update2

    OCTOBER 2023

  • Project Update1

    SEPTEMBER 2023 Existing ceiling demo  (ceiling demo west)  Scaffold Photos Project Signs Slab Edge Demo (slab edge demo 1)  (slab edge demo 3)